An Oil and Gas terminal had mixed 350 BBL of product inside a pipeline. The company was going to push the mixed product to a LPG transport truck using a pig, and Envent was requested to control vapors on the truck to prevent it from overpressuring. Successfully purged the pipeline of the mixed product in 6 hours of operation.
- All
- /Case Studies
- /Compression
- /Degassing
- /GHG Emission Control
- /Marine Vapor Recovery
- /Mobile Water Treatment
- /Odor Control
- /Soil Vapor Extraction and Remediation Systems
- /Turnaround Services
- /Vapor Control
- /Vapor Scrubbing
-
-
Southern California Tank Degassing
A 180,000 BBL Southern California refinery wastewater tank, frac tanks and centrifuge equipment needed vapor control and degassing during sludge removal. The two month long project needed redundancy and great attention to detail to abide by the permitting requirements. Maintained 24/7 operation while making the short generator service intervals.
-
Houston Area, Refinery Turnaround Support Services
The challenge was to handle the vapor control for 250 frac tanks and the blow downs from the towers, columns, and vapors from the vacuum trucks. Envent’s 24 hour manned operation ensured the tank was degassed correctly and safely.
-
Los Angeles, California, Major Oil Pipeline Emergency Water Treatment
A pipeline company required emergency treatment and discharge of contaminated water to the Los Angeles City Sanitation system during a construction project. The effluent pipeline water properties varied over time due to numerous drilling and grouting activities occurring upstream of the effluent.
-
Alaska – 3 Million Gallons Hydrotest & Water Treatment
Treat and discharge 3,000,000 gallons of water from a pipeline hydrotest on the North Slope of Alaska. Protected America’s last frontier while minimizing costs.
-
Port Arthur, TX, Chemical Plant Benzene Tank Degassing
A chemical plant in Texas required a 24,000 barrel tank to be degassed during, and following a tank cleaning. Degassing Tanks under a Nitrogen Blanket Not a Problem for Envent.
-
Pennsylvania Refinery, Pipeline Degassing
During a pipeline re-commissioning a leak was detected requiring 12,000 barrels of propane needing to be combusted. By using the vapors in two ways, the time to depressure the pipeline was completed 4 times as fast.
-
San Francisco, Gasoline Barge Degassing
An energy and industrial services company needed to degas 10 compartments barge in California. Quick and effectively was required. Envent degassed each compartment in 2 hours, with a 99.9% destruction efficiency.
-
Kentucky Refinery, Emergency Tank Degas
A tank farm customer requested Envent be onsite for an unscheduled tank refill within 4 hours. Envent was able to respond to the emergency quickly and safely, which saved the customer thousands of dollars in down time.
-
Central California Dewatering and Treatment for Soil Excavation
A customer at a Super Fund Site in Central California needed support to dewater a pit dug in a neighborhood in order to remove contaminated soil. Cost of treating and discharging the water was at a fraction of the cost.
-
Northern California, Pipeline Blowdown
A pipeline company in Northern California needed to blow down their natural gas pipeline for repairs and inspection. Four volume line sweeps were performed to leave the piping free of residual gas.