Challenge A client asked Envent to help them to do the vapor control on the fuel gas recovery line at their refinery during their hydrogen plant turnaround event. As the hydrogen plant was being taken offline, the refinery fuel gas consumption would decrease, causing an excess of fuel gas. The excess capacity of the […]
- All
- /Case Studies
- /Compression
- /Degassing
- /GHG Emission Control
- /Marine Vapor Recovery
- /Mobile Water Treatment
- /Odor Control
- /Soil Vapor Extraction and Remediation Systems
- /Turnaround Services
- /Vapor Control
- /Vapor Scrubbing
-
-
Pipeline Clearing + LPG Bullet Depressurization and Degas
Challenge A customer in the Gulf Coast engaged Envent with the need to depressure and clear a pipeline running from its refinery to 3.5 miles South of refinery for an emergency repair and inspection. The customer also brought up the need to a depressurization and de-inventory for an LPG Bullet tank during the same time […]
-
Envent Provides Vapor Recovery System to Underground Toxic Cleanup
Challenge A chemical manufacturing facility in the Southeastern US had a large underground cleanup of toxic chemicals that had been spreading underground for many years. They had a design for the tent enclosure that the heavy equipment would be working in but needed a vapor recovery system to make sure none of the hazardous vapors […]
-
Envent Engineers ensure Environmental Compliance
Challenge Envent provided vapor control on 5 temporary frac tanks during a tank cleaning. The source tank was emptied of a slop oil mixture. The product was going to be separated by a centrifuge into water, oil, and solid components. The temporary tanks in use accepted water/oil outputs and contained a heavy oil/sludge input […]
-
Envent helps to provide a solution to handle Liquid Ammonia
Challenge A customer tasked Envent to help evacuate an Ammonia tank skid and the surrounding piping so that multiple valves in the system could be replaced safely. Envent would have to provide a solution to handle liquid ammonia, associated temperature issues, and chemical hazards. Solution Envent provided the customer with a High Pressure Regulator, a […]
-
Degassing of an LNG-powered Freight Vessel
Envent’s depressure solution allowed for the customer to successfully continue operations without having to delay any standard procedures. In addition, the customer was able to start maintenance work on both LNG tanks immediately after this process was completed. Both of these achievements allowed the customer to save a valuable amount of time and money.
-
Three Phase Permitted Vapor Control
Envent developed a three phase vapor odor control solution for a Pacific Northwest customer utilizing a recirculating scrubber (for H2S removal) and a high flow thermal oxidizer to safely eliminate nuisance odors to the surrounding community as well as maintain 100% compliance and zero fines.
-
Port of Brownsville, TX – Tank Degas
Challenge A customer in the Port of Brownsville; the tank was a mid-sized High RVP Gasoline tank with a pipeline feeding into it. The tank was due to come out of service for an API 653 inspection. The customer as well as cleaning company had assumed the tank to be product free, but upon closer […]
-
West Texas Terminal – 3 Tank Vapor Control
Challenge A large Oil and Gas customer needed to perform maintenance on 3 tanks in one of their West Texas terminals. The majority of the maintenance was focused on removing and replacing the shell-side mixers. The problem was that those same tanks were critical to their day to day operations, meaning that the turnaround time […]
-
Depressurization of a Panhandle LPG Pipeline
Challenge Envent was challenged with depressurizing a propane line, within the confines of a gulf coast refinery. The line measured over 2 miles, was above 200 psig, and was full of liquid propane gas. Envent needed to ensure the pipeline was cleared and ready for Hotwork within a 2 day time frame due to inclement […]
-
Port Arthur Refinery – H2S Scrubber Control
Challenge A customer was facing EPA fines in the tens of thousands of dollars per day for the release of H2S and VOC’s to atmosphere from a tank not permitted to contain H2S-laden material. The customer reached out to Envent to solve the problem within a short deadline of three months. Solution Envent was […]
-
RTO Breakdown Emergency Mobile Replacement
West Coast customer challenged Envent to create an immediate temporary solution which would enable them to continue production during the 1.5 month lead time it would take to manufacture, transport, and install their new system.